| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | JAKSON - VISHVARAJ (JV) | 20094521 | Parsa Chaubey Gram Panchayat Water Supply Scheme | 168.00 | 78.06 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 4656.00 | 4602.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sant Kabeer Nagar | Mehdawal | Parsa Chaubey | 451979 | Parsa Chaubey | 110 | 110 | 100 | Har Gar Jal | Not Certified |
| 2 | Sant Kabeer Nagar | Mehdawal | Parsa Chaubey | 451980 | Bhitia Khurd | 76 | 76 | 100 | Har Gar Jal | Not Certified |
| 3 | Sant Kabeer Nagar | Mehdawal | Parsa Chaubey | 659672 | PARSADEEH | 10 | 10 | 100 | Har Gar Jal | Not Certified |