Scheme Details
DISTRICT Raebareli
AGENCY NCC Ltd.
SCHEME ID 20094579
SCHEME NAME Bawan Buzurg Valla Water Supply Scheme
ESTIMATED COST 1110.32
EXPENDITURE 553.51
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 2
Work Started 0
Work Completed 0
Solar Plant
Required 84
Procured 84 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 60368.00 Meter
Length Laid 37380.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Raebareli Amawan Bawan Buzurg Valla 416679 Bawan Buzurg Valla 2335 2143 92% Work In Progress Not Certified