Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Prayagraj
AGENCY Larsen & Toubro Ltd
SCHEME ID 20094827
SCHEME NAME RAMNAGER-MIRAPUR-CHANDERPUR URF BUSMAHUA WATER SUPPLY SCHEME
ESTIMATED COST 453.18
EXPENDITURE 234.73
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 49
Procured 0 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 30801.00 Meter
Length Laid 30801.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Prayagraj Bahariya Chanderpur Urf Basmahua 432126 Chanderpur Urf Basmahua 615 611 99% Work In Progress Not Certified
2 Prayagraj Bahadurpur Meerapur 432535 Mirapur 160 131 82% Work In Progress Not Certified
3 Prayagraj Bahadurpur Ramnager 432554 Ramnager 226 214 95% Work In Progress Not Certified