Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20094852 | AMAURA REORGANISATION W/S SCHEME (VSA) | 1688.40 | 50.88 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Bhadaura | Amaura | 474020 | Amaura | 533 | 510 | 96 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Bhadaura | Baksara | 474037 | Baksara | 402 | 375 | 93 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Bhadaura | Suraha | 474052 | Suraha | 210 | 203 | 97 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Bhadaura | Misraulia | 474053 | Misraulia | 200 | 179 | 90 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Bhadaura | Dehwal | 474087 | Dehwal | 77 | 72 | 94 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 5 | 5 | 5 | 5 | 4 | 4 | 0 | 105 | 105 | NA | 0 | NA | No | 50468.00 | 49853.00 |