Scheme Details
DISTRICT
Saharanpur
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20094857
SCHEME NAME
Saroorpur Taga & Nakur Dehat GP WSS
ESTIMATED COST
407.92
EXPENDITURE
122.50
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12788.00
Meter
Length Laid
12745.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Nakur | Saroorpur Taga | 384056 | Saroorpur Taga | 278 | 272 | 98% | Work In Progress | Not Certified |
| 2 | Saharanpur | Nakur | Saroorpur Taga | 384171 | Shahpur Taga | 20 | 14 | 70% | Work In Progress | Not Certified |
| 3 | Saharanpur | Nakur | Nakur Dehat | 384172 | Nakur(dehat) | 372 | 364 | 98% | Work In Progress | Not Certified |