Scheme Details
DISTRICT
Gautam Buddha Nagar
AGENCY
LC INFRA
SCHEME ID
20094858
SCHEME NAME
JARCHA REORGNISATION WATER SUPPLY SCHEME
ESTIMATED COST
771.00
EXPENDITURE
638.83
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
65
Procured
65
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24883.00
Meter
Length Laid
25387.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gautam Buddha Nagar | Dadari | Jarcha | 392803 | Jarcha | 2809 | 2809 | 100% | Har Ghar Jal | Not Certified |