Scheme Details
DISTRICT
Ghazipur
AGENCY
VSA
SCHEME ID
20094878
SCHEME NAME
BADHARA REORGANISATION W/S SCHEME (VSA)
ESTIMATED COST
434.04
EXPENDITURE
199.72
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
21
Procured
21
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23045.00
Meter
Length Laid
22890.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Turana | 472349 | Turana | 257 | 254 | 99% | Work In Progress | Not Certified |
| 2 | Ghazipur | Deokali | Badahra | 472503 | Badahra | 277 | 274 | 99% | Work In Progress | Not Certified |