Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20094878 | BADHARA REORGANISATION W/S SCHEME (VSA) | 434.04 | 170.41 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 21 | 21 | Yes | 0 | NA | No | 23045.00 | 22890.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Turana | 472349 | Turana | 257 | 221 | 86 | Work In Progress | Not Certified |
| 2 | Ghazipur | Deokali | Badahra | 472503 | Badahra | 277 | 239 | 86 | Work In Progress | Not Certified |