Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20094892 | BADHAURA REORGANISATION W/S SCHEME (VSA) | 537.12 | 4.07 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Bhadaura | Bhadauraa | 474044 | Bhadaura | 444 | 281 | 63 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Bhadaura | Bhadauraa | 474045 | Rajaipur Urf Rajpur | 15 | 1 | 7 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Bhadaura | Bhadauraa | 474046 | Rampur Urf Ramgarh | 1 | 1 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ghazipur | Bhadaura | Sawrai | 474083 | Sawrai | 1882 | 1882 | 100 | Har Gar Jal | Not Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 35 | 35 | Yes | 0 | NA | No | 18655.00 | 17534.00 |