| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | VSA | 20094930 | DEOKALI REORGANISATION W/S SCHEME (VSA) | 223.70 | 17.86 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | NA | 10 | NA | No | 8810.00 | 7047.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Bhadaura | Deokalee | 474030 | Deokali | 388 | 342 | 88 | Work In Progress | Not Certified |
| 2 | Ghazipur | Bhadaura | Deokalee | 474031 | Ghoswal | 15 | 6 | 40 | Work In Progress | Not Certified |