Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20094947 | BAIDOLIYA, HARDI KHAS & KHUTHNA GP wss | 401.18 | 118.99 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 38 | 38 | Yes | 0 | NA | No | 23311.00 | 23000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Hardi Khas | 449520 | Hardi Khas | 401 | 399 | 100 | Work In Progress | Not Certified |
| 2 | Basti | Gaur | Khutahana | 449525 | Khutahana | 147 | 146 | 99 | Work In Progress | Not Certified |
| 3 | Basti | Gaur | Baidoliya | 449526 | Baidauliya | 101 | 100 | 99 | Work In Progress | Not Certified |
| 4 | Basti | Gaur | Khutahana | 449527 | Banktiya | 104 | 103 | 99 | Work In Progress | Not Certified |
| 5 | Basti | Gaur | Baidoliya | 449528 | Ramawapur | 55 | 55 | 100 | Har Gar Jal | Not Certified |
| 6 | Basti | Gaur | Khutahana | 680662 | Deo Rahana | 6 | 5 | 83 | Work In Progress | Not Certified |