Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20094958 | RANEEPUR REORGANISATION W/S SCHEME (VSA) | 940.54 | 250.33 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Mardah | Fatehpur | 472706 | Fatehpur | 159 | 109 | 69 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Mardah | Fatehpur | 472707 | Hasanpura | 34 | 15 | 44 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Mardah | Raneepur | 472747 | Ranipur | 702 | 452 | 64 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Mardah | Raneepur | 472748 | Narangpur | 91 | 37 | 41 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 4 | 4 | 4 | 4 | 2 | 0 | 1 | 53 | 53 | Yes | 0 | NA | No | 46871.00 | 46568.00 |