Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | VSA | 20094981 | BASUPUR REORGANISATION W/S SCHEME (VSA) | 695.80 | 230.95 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Deokali | Khijir Pur | 472320 | Khijir Pur | 144 | 132 | 92 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Deokali | Khijir Pur | 472321 | Nasirpur | 100 | 88 | 88 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Deokali | Basu Pur | 472403 | Basu Pur | 149 | 149 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Ghazipur | Deokali | Basu Pur | 472404 | Kanali | 117 | 99 | 85 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Deokali | Sehamal Pur | 472478 | Sehamal Pur | 173 | 145 | 84 | Work In Progress | Not Certified | Not Verified |
6 | Ghazipur | Deokali | Sehamal Pur | 472479 | Bir Singhpur | 41 | 21 | 51 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
6 | 4 | 4 | 4 | 4 | 3 | 3 | 0 | 32 | 32 | Yes | 0 | NA | No | 34260.00 | 32464.00 |