Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Megha | 20095014 | SARAY PANDEY & CHHANDRAULI Water Supply Scheme | 701.45 | 234.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 25930.00 | 22630.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Triveniganj | Sarai Pandey | 436021 | Sarai Pandey | 975 | 968 | 99 | Work In Progress | Not Certified |
| 2 | Barabanki | Triveniganj | Sarai Pandey | 436022 | Sadruddin Pur | 155 | 147 | 95 | Work In Progress | Not Certified |
| 3 | Barabanki | Triveniganj | Chhandrauli | 436031 | Chhandrauli | 466 | 458 | 98 | Work In Progress | Not Certified |