Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20095027
SCHEME NAME
RAMAPUR_SHAHARI BOJH WATER SUPPLY SCHEME
ESTIMATED COST
312.90
EXPENDITURE
91.73
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23705.00
Meter
Length Laid
23500.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Dhanoopur | Ramapur | 433436 | Rampur | 133 | 107 | 80% | Work In Progress | Not Certified |
| 2 | Prayagraj | Dhanoopur | Ramapur | 433437 | Samala Patti | 79 | 77 | 97% | Work In Progress | Not Certified |
| 3 | Prayagraj | Dhanoopur | Shahari Bojh | 433442 | Shahari Bojh | 296 | 271 | 92% | Work In Progress | Not Certified |