Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Mau | KLSR - RAYS (JV) | 20095044 | BANDI KALA WATER SUPPLY SCHEME | 297.28 | 119.87 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | Yes | 0 | NA | No | 12628.00 | 10562.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Muhammadabad Gohana | Bandi Kala | 466016 | Bandi Kala | 512 | 500 | 98 | Work In Progress | Not Certified | 
| 2 | Mau | Muhammadabad Gohana | Bandi Kala | 466019 | Farid Pur | 10 | 1 | 10 | Work In Progress | Not Certified | 
| 3 | Mau | Muhammadabad Gohana | Bandi Kala | 677831 | Chakjarullah | 5 | 1 | 20 | Work In Progress | Not Certified | 
| 4 | Mau | Muhammadabad Gohana | Bandi Kala | 678146 | Chakwasha | 2 | 1 | 50 | Work In Progress | Not Certified |