Scheme Details
DISTRICT Mau
AGENCY GA INFRA-VPL
SCHEME ID 20095047
SCHEME NAME BANKARA KHURD & SULTANPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 271.09
EXPENDITURE 242.09
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 21
Procured 21 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14957.00 Meter
Length Laid 14097.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Badraon Sultanpur 465254 Sultanpur 220 214 97% Work In Progress Not Certified
2 Mau Badraon Bankara Khud 465255 Patna 21 19 90% Work In Progress Not Certified
3 Mau Badraon Bankara Khud 465256 Bankara Khurd 148 140 95% Work In Progress Not Certified