Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Mau | GA INFRA-VPL | 20095067 | BELA GADAYANPATTI GRAM PANCHAYAT WATER SUPPLY SCHEME | 229.47 | 144.94 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 13 | 13 | NA | 0 | NA | No | 15279.00 | 14614.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Fatehpur Madraun | Bela Gadayanpatti | 465382 | Bela Gadayanpatti | 255 | 255 | 100 | Har Gar Jal | Not Certified | 
| 2 | Mau | Fatehpur Madraun | Bela Gadayanpatti | 465383 | Parasiya Kaishapur | 45 | 45 | 100 | Har Gar Jal | Not Certified |