Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20095079 | DUBRAHAN KHURD AND MOHIDDENPUR-II water supply scheme | 371.20 | 152.56 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 27 | 27 | Yes | 0 | NA | No | 14064.00 | 13500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Bilariaganj | Dubrahan Khurd | 462044 | Dubrahan Kurd | 107 | 105 | 98 | Work In Progress | Not Certified |
| 2 | Azamgarh | Bilariaganj | Dubrahan Khurd | 462045 | Jaloopur | 80 | 74 | 92 | Work In Progress | Not Certified |
| 3 | Azamgarh | Bilariaganj | Mohiddenpur Ii | 462182 | Mohiddenpur | 130 | 127 | 98 | Work In Progress | Not Certified |
| 4 | Azamgarh | Bilariaganj | Mohiddenpur Ii | 462184 | Pandey Pokher | 48 | 43 | 90 | Work In Progress | Not Certified |
| 5 | Azamgarh | Bilariaganj | Mohiddenpur Ii | 692308 | KHARUDEENPUR | 84 | 81 | 96 | Work In Progress | Not Certified |
| 6 | Azamgarh | Bilariaganj | Mohiddenpur Ii | 701841 | SAIDPUR | 8 | 6 | 75 | Work In Progress | Not Certified |