Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20095291
SCHEME NAME
BALELPUR WATER SUPPLY SCHEME
ESTIMATED COST
283.27
EXPENDITURE
68.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12275.00
Meter
Length Laid
11200.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Meh Nagar | Balelpur | 464747 | Ebrahimpur | 61 | 59 | 97% | Work In Progress | Not Certified |
| 2 | Azamgarh | Meh Nagar | Balelpur | 464749 | Raipur Kaji Mali | 106 | 106 | 100% | Har Ghar Jal | Not Certified |
| 3 | Azamgarh | Meh Nagar | Balelpur | 464750 | Balelpur | 115 | 115 | 100% | Har Ghar Jal | Not Certified |