Scheme Details
DISTRICT Mau
AGENCY KLSR - RAYS (JV)
SCHEME ID 20095473
SCHEME NAME DHARMSIPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 408.30
EXPENDITURE 177.36
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 29604.00 Meter
Length Laid 25986.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Ranipur Dharmsipur 466084 Dharmsipur 521 500 96% Work In Progress Not Certified
2 Mau Ranipur Dharmsipur 466085 Sonjan 45 12 27% Work In Progress Not Certified
3 Mau Ranipur Dharmsipur 466086 Chakson 47 34 72% Work In Progress Not Certified
4 Mau Ranipur Dharmsipur 466087 Karjauli 103 76 74% Work In Progress Not Certified