Scheme Details
DISTRICT Mau
AGENCY GA INFRA-VPL
SCHEME ID 20095495
SCHEME NAME KAPARIYADIH GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST 310.21
EXPENDITURE 259.30
AUTOMATION STATUS
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 25
Procured 25 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 17966.00 Meter
Length Laid 17246.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Badraon Kapariyadih 465251 Kapariyadih 400 392 98% Work In Progress Not Certified
2 Mau Badraon Kapariyadih 465252 Katai Chawar 92 82 89% Work In Progress Not Certified