Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Larsen & Toubro Ltd | 20095535 | Lokapur (Revision) | 197.11 | 108.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 11 | 11 | Yes | 0 | NA | No | 13034.00 | 13630.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Pindara | Lokapur | 475792 | MAGHMITIYA | 17 | 0 | 0 | Work In Progress | Not Certified |
| 2 | Varanasi | Pindara | Lokapur | 475793 | Dayalpur Kala | 22 | 22 | 100 | Har Gar Jal | Certified |
| 3 | Varanasi | Pindara | Lokapur | 475794 | Dayalpur Khurd | 20 | 20 | 100 | Har Gar Jal | Certified |
| 4 | Varanasi | Pindara | Lokapur | 475795 | Lokapur | 172 | 172 | 100 | Har Gar Jal | Certified |