Scheme Details
DISTRICT
Bijnor
AGENCY
LC INFRA
SCHEME ID
20095831
SCHEME NAME
BHANERA (ZONE-I) VILLAGE WSS
ESTIMATED COST
553.97
EXPENDITURE
410.25
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
20
Transformer Procured
Yes
Work Status
No
Distribution Line
Total Length
24603.00
Meter
Length Laid
24597.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kiratpur | Bhanera | 385816 | Bhanera | 432 | 432 | 100% | Har Ghar Jal | Certified |
| 2 | Bijnor | Kiratpur | Bhanera | 385817 | Mubarakpur Mira | 1611 | 1611 | 100% | Har Ghar Jal | Not Certified |