Scheme Details
DISTRICT Siddharth Nagar
AGENCY JAKSON - VISHVARAJ (JV)
SCHEME ID 20096335
SCHEME NAME DABRA GP WSS
ESTIMATED COST 135.55
EXPENDITURE 61.56
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 2816.00 Meter
Length Laid 3200.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Siddharth Nagar Itwa Dabara 448088 Dabra 142 89 63% Work In Progress Not Certified
2 Siddharth Nagar Itwa Dabara 448089 PAIKI SHUKLA 113 36 32% Work In Progress Not Certified