Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pilibhit
AGENCY PNC-SPML-JV
SCHEME ID 20096372
SCHEME NAME Barahi & Narayanpur Buzurg water supply scheme
ESTIMATED COST 515.65
EXPENDITURE 439.38
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 62816.00 Meter
Length Laid 62816.00 Meter

Scheme Assigned Villages

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Puranpur Barahi 405340 Barahi 55 53 96% Work In Progress Not Certified
2 Pilibhit Puranpur Barahi 405341 Basantpur Nauner 242 241 100% Work In Progress Not Certified
3 Pilibhit Puranpur Narayanpur Bujurg 405578 Narayanpur Bujurg 307 303 99% Work In Progress Not Certified
4 Pilibhit Puranpur Narayanpur Bujurg 405579 Rajpur T. Madhau Tanda 99 98 99% Work In Progress Not Certified
5 Pilibhit Puranpur Narayanpur Bujurg 405580 Makrandpur Chaugan 109 108 99% Work In Progress Not Certified