Scheme Details
DISTRICT
Azamgarh
AGENCY
LC INFRA
SCHEME ID
20096423
SCHEME NAME
Rasulpur Baisar Water Supply Scheme
ESTIMATED COST
193.09
EXPENDITURE
190.10
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9651.00
Meter
Length Laid
8000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Mirzapur | RASULPUR BAISAR | 463449 | Rasulpur | 474 | 473 | 100% | Work In Progress | Not Certified |
| 2 | Azamgarh | Mirzapur | RASULPUR BAISAR | 463450 | Bausar | 66 | 61 | 92% | Work In Progress | Not Certified |
| 3 | Azamgarh | Mirzapur | RASULPUR BAISAR | 463451 | Sansarpur | 17 | 16 | 94% | Work In Progress | Not Certified |
| 4 | Azamgarh | Mirzapur | RASULPUR BAISAR | 680466 | Rasulpur Kajiyakubpur | 6 | 1 | 17% | Work In Progress | Not Certified |