Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20096632
SCHEME NAME Inta Rora GP water supply scheme
ESTIMATED COST 143.87
EXPENDITURE 116.61
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 8
Transformer Procured NA
Work Status No
Distribution Line
Total Length 2548.00 Meter
Length Laid 2456.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Barkhera Inta Rora 404967 Inta Rora 262 262 100% Har Ghar Jal Certified