Scheme Details
DISTRICT
Chandauli
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20096766
SCHEME NAME
Amara WS
ESTIMATED COST
273.80
EXPENDITURE
253.98
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
8
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9176.00
Meter
Length Laid
9401.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chakiya | Amara | 475151 | Amara Uttari | 326 | 326 | 100% | Har Ghar Jal | Certified |
| 2 | Chandauli | Chakiya | Amara | 475152 | Muglalpurwa | 82 | 82 | 100% | Har Ghar Jal | Certified |
| 3 | Chandauli | Chakiya | Amara | 657093 | Bhatouli | 17 | 17 | 100% | Har Ghar Jal | Certified |