Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20096839 | BENIGANJ DEHAT JJM | 886.36 | 468.09 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 2 | 0 | 2 | 64 | 64 | Yes | 0 | NA | No | 18432.00 | 19927.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | KOTHAWAN | SADIPUR | 413299 | SADIPUR | 601 | 601 | 100 | Har Gar Jal | Certified |
| 2 | Hardoi | KOTHAWAN | BENIGANJ DEHAT | 413341 | BENIGANJ DEHAT | 1517 | 1516 | 100 | Work In Progress | Not Certified |