Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20096873 | MAROOFPUR VILLAGE WATER SUPPLY SCHEME | 294.15 | 118.75 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | Yes | 0 | NA | No | 10117.00 | 9585.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Shahganj | Chakmaroof Pur | 468395 | Majhaura | 138 | 87 | 63 | Work In Progress | Not Certified |
| 2 | Jaunpur | Shahganj | Maroofpur | 468396 | Maroofpur | 134 | 120 | 90 | Work In Progress | Not Certified |
| 3 | Jaunpur | Shahganj | Maroofpur | 468397 | Jamin Rudhauli | 121 | 116 | 96 | Work In Progress | Not Certified |
| 4 | Jaunpur | Shahganj | Chakmaroof Pur | 468404 | Chakmaroof Pur | 138 | 80 | 58 | Work In Progress | Not Certified |