Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20096890
SCHEME NAME
Jamalpur water supply scheme
ESTIMATED COST
466.72
EXPENDITURE
184.85
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
0
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16815.00
Meter
Length Laid
3000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Palhani | Jamalpur | 462937 | Jamalpur | 387 | 381 | 98% | Work In Progress | Not Certified |
| 2 | Azamgarh | Palhani | Jamalpur | 462938 | Rampur Japati | 111 | 99 | 89% | Work In Progress | Not Certified |
| 3 | Azamgarh | Palhani | Jamalpur | 462939 | Arjibenkateya | 4 | 2 | 50% | Work In Progress | Not Certified |