Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Saharanpur | NKG-PRIMUS (JV) | 20096911 | KHIZARPUR CHAK MUSTAFAPUR MV WSS | 285.47 | 27.25 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Saharanpur | Sadhauli Kadeem | Khizarpur Chack Mutafapur | 383501 | Alipur Damanki | 73 | 1 | 1 | Work In Progress | Not Certified | Not Verified |
2 | Saharanpur | Sadhauli Kadeem | Khizarpur Chack Mutafapur | 383502 | Meerpur Thasaka Jadid | 166 | 1 | 1 | Work In Progress | Not Certified | Not Verified |
3 | Saharanpur | Sadhauli Kadeem | Khizarpur Chack Mutafapur | 383503 | Meerpur Thasak Kadim | 44 | 1 | 2 | Work In Progress | Not Certified | Not Verified |
4 | Saharanpur | Sadhauli Kadeem | Khizarpur Chack Mutafapur | 383504 | Khizarpur Chack Mustafapur | 249 | 1 | 0 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | NA | 25 | NA | No | 12871.00 | 0.00 |