Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20097007
SCHEME NAME
RASOOLPUR ABAD WSS
ESTIMATED COST
1210.40
EXPENDITURE
821.69
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
81
Procured
38
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
52197.00
Meter
Length Laid
49733.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Afajalganj(kasampur Garhi) | Rasoolpur Abad | 386810 | Rasoolpur Abad | 1356 | 1356 | 100% | Har Ghar Jal | Not Certified |