Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20097096 | NAVADA & SHEKHPUR W/S SCHEME (HFCL) | 324.19 | 71.81 | Verified | Verified | view more |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Saidpur | Shekhpur | 472236 | Shekhpur | 183 | 165 | 90 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Saidpur | NEVADA | 472277 | NAVADA | 175 | 175 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Ghazipur | Saidpur | NEVADA | 472278 | CHAKIYA MASON | 144 | 144 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 8 | NA | No | 15877.00 | 11478.20 |