Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Rithwik-Koya (JV) | 20097104 | Pipra bishambharpur & Odhawaliya GOV Water Supply Scheme | 396.38 | 147.82 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 18521.00 | 18921.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Pharenda | ODVALIYA | 454131 | AODVALIYA | 114 | 83 | 73 | Work In Progress | Not Certified |
| 2 | Maharajganj | Pharenda | ODVALIYA | 454132 | RATNPUR URF BHERTHIPUR | 80 | 60 | 75 | Work In Progress | Not Certified |
| 3 | Maharajganj | Pharenda | Pipra Bisvmabhrapur | 454146 | Pipra Bisvmabhrapur | 330 | 329 | 100 | Work In Progress | Not Certified |