Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20097114
SCHEME NAME
KHOJANPUR W/S SCHEME
ESTIMATED COST
299.14
EXPENDITURE
110.85
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15890.00
Meter
Length Laid
15145.00
Meter
Scheme Assigned Villages
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Khojanpur | 472322 | Khojanpur | 130 | 128 | 98% | Work In Progress | Not Certified |
| 2 | Ghazipur | Deokali | Khojanpur | 472323 | Chakphatma Urf Balua | 45 | 43 | 96% | Work In Progress | Not Certified |
| 3 | Ghazipur | Deokali | Khojanpur | 472324 | Chakwaj Urph Bhatpurwa | 30 | 30 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ghazipur | Deokali | Khojanpur | 472325 | Wikachak | 84 | 77 | 92% | Work In Progress | Not Certified |
| 5 | Ghazipur | Deokali | Khojanpur | 472326 | Sikandarpur | 89 | 87 | 98% | Work In Progress | Not Certified |