Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ghazipur
AGENCY Larsen & Toubro Ltd
SCHEME ID 20097114
SCHEME NAME KHOJANPUR W/S SCHEME
ESTIMATED COST 299.14
EXPENDITURE 110.85
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15890.00 Meter
Length Laid 15145.00 Meter

Scheme Assigned Villages

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ghazipur Deokali Khojanpur 472322 Khojanpur 130 128 98% Work In Progress Not Certified
2 Ghazipur Deokali Khojanpur 472323 Chakphatma Urf Balua 45 43 96% Work In Progress Not Certified
3 Ghazipur Deokali Khojanpur 472324 Chakwaj Urph Bhatpurwa 30 30 100% Har Ghar Jal Not Certified
4 Ghazipur Deokali Khojanpur 472325 Wikachak 84 77 92% Work In Progress Not Certified
5 Ghazipur Deokali Khojanpur 472326 Sikandarpur 89 87 98% Work In Progress Not Certified