Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20097116
SCHEME NAME
SHIVEPUR W/S SCHEME
ESTIMATED COST
231.41
EXPENDITURE
128.77
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
14
Procured
14
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18394.00
Meter
Length Laid
14000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | Shivepur | 471610 | Shivepur | 214 | 209 | 98% | Work In Progress | Not Certified |
| 2 | Ghazipur | Jakhania | Shivepur | 471611 | Narayanpur | 68 | 68 | 100% | Har Ghar Jal | Not Certified |