Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Larsen & Toubro Ltd | 20097119 | BHAKHRA W/S SCHEME | 204.38 | 53.99 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 11 | 11 | NA | 0 | NA | No | 12210.00 | 10153.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Manihari | Khakhra | 471775 | Khakhra | 129 | 89 | 69 | Work In Progress | Not Certified |
| 2 | Ghazipur | Manihari | Khakhra | 471776 | Chak Raham | 49 | 1 | 2 | Work In Progress | Not Certified |
| 3 | Ghazipur | Manihari | Khakhra | 471777 | Fanikarna | 49 | 1 | 2 | Work In Progress | Not Certified |