Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Gorakhpur
AGENCY NCC Ltd.
SCHEME ID 20097150
SCHEME NAME Mirhrya Water Suppy System
ESTIMATED COST 177.92
EXPENDITURE 162.95
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 3036.00 Meter
Length Laid 2894.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Gorakhpur Campiere Ganj Mirhiriya 454636 Mirhiriya 332 330 99% Work In Progress Not Certified