Scheme Details
DISTRICT
Barabanki
AGENCY
Megha
SCHEME ID
20097162
SCHEME NAME
Aluwamau Water Supply Scheme
ESTIMATED COST
143.98
EXPENDITURE
74.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
3289.00
Meter
Length Laid
2938.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Siddhaur | Aluwa Mau | 435893 | Kala Pur | 79 | 77 | 97% | Work In Progress | Not Certified |
| 2 | Barabanki | Siddhaur | Aluwa Mau | 435894 | Aluwa Mau | 146 | 144 | 99% | Work In Progress | Not Certified |