Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20097185
SCHEME NAME
Sikandarpur Water Supply Scheme
ESTIMATED COST
150.28
EXPENDITURE
46.49
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
63
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
4881.00
Meter
Length Laid
4881.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Dewa | Sikandarpur | 435084 | Sikandarpur | 103 | 101 | 98% | Work In Progress | Not Certified |
| 2 | Barabanki | Dewa | Sikandarpur | 435085 | Umar Pur | 86 | 79 | 92% | Work In Progress | Not Certified |