Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20097210
SCHEME NAME
HAREDAR BUZURG Water Supply Scheme
ESTIMATED COST
258.20
EXPENDITURE
257.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11033.00
Meter
Length Laid
16032.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Hata Khurd | 455867 | Gopalpur | 187 | 187 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Uruwa | Haradar Bujurg | 455895 | Haradar Bujurg | 145 | 145 | 100% | Har Ghar Jal | Certified |
| 3 | Gorakhpur | Uruwa | Haradar Bujurg | 455896 | Indrapur Khurd | 26 | 26 | 100% | Har Ghar Jal | Certified |
| 4 | Gorakhpur | Uruwa | Haradar Bujurg | 455898 | Araji Haredand Khurd | 1 | 1 | 100% | Har Ghar Jal | Certified |
| 5 | Gorakhpur | Uruwa | Haradar Bujurg | 455899 | Indupur Bujurg | 6 | 6 | 100% | Har Ghar Jal | Certified |
| 6 | Gorakhpur | Uruwa | Haradar Bujurg | 455900 | Teliyabhar Urf Bisunpur | 99 | 99 | 100% | Har Ghar Jal | Certified |
| 7 | Gorakhpur | Uruwa | Haradar Bujurg | 693155 | GOPALPUR | 86 | 86 | 100% | Har Ghar Jal | Certified |