Scheme Details
DISTRICT
Shravasti
AGENCY
GA INFRA-VPL
SCHEME ID
20097249
SCHEME NAME
BAKWA
ESTIMATED COST
475.77
EXPENDITURE
242.47
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
2
Work Started
1
Work Completed
0
Solar Plant
Required
36
Procured
0
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
26511.00
Meter
Length Laid
25253.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Sirsiya | Bakwa | 443247 | Bakwa | 715 | 715 | 100% | Har Ghar Jal | Certified |