Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Shravasti
AGENCY GA INFRA-VPL
SCHEME ID 20097302
SCHEME NAME MADRAHVA_ BELHARI
ESTIMATED COST 490.54
EXPENDITURE 262.43
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 2
Work Started 0
Work Completed 0
Solar Plant
Required 29
Procured 29 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 25225.00 Meter
Length Laid 21037.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Shravasti Sirsiya Madrahva 443217 Madrahva 294 284 97% Work In Progress Not Certified
2 Shravasti Sirsiya Belhari 443218 Belhari 313 293 94% Work In Progress Not Certified