Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Deoria | LC INFRA | 20097406 | HETIMPUR GP RO SCHEME | 381.50 | 181.13 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 23 | 23 | NA | 0 | NA | No | 23007.00 | 19000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Desai Deoria | Hetimpur | 459142 | Hetimpur | 1106 | 1106 | 100 | Har Gar Jal | Not Certified |
| 2 | Deoria | Desai Deoria | Hetimpur | 459143 | Jigani Musahib Khan | 37 | 37 | 100 | Har Gar Jal | Not Certified |