Scheme Details
DISTRICT
Deoria
AGENCY
LC INFRA
SCHEME ID
20097424
SCHEME NAME
BAGHAUCH GHAT GP RO SCHEME
ESTIMATED COST
291.49
EXPENDITURE
177.92
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
15
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21536.00
Meter
Length Laid
20000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Deoria | Pathardewa | Baghauch | 459109 | Baghauch | 596 | 596 | 100% | Har Ghar Jal | Not Certified |