Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | NCC Ltd. | 20097636 | BAGHRAYEE&LALPUR Water Supply Scheme | 524.78 | 357.69 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Gorakhpur | Bansgaon | Baghrayee | 456089 | Baghrayee | 436 | 436 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Gorakhpur | Bansgaon | Baghrayee | 456090 | Mahuapar | 32 | 32 | 100 | Har Gar Jal | Not Certified | Not Verified |
3 | Gorakhpur | Bansgaon | Baghrayee | 456091 | Jari | 87 | 87 | 100 | Har Gar Jal | Not Certified | Not Verified |
4 | Gorakhpur | Bansgaon | Baghrayee | 456092 | Dumari Baboo | 39 | 39 | 100 | Har Gar Jal | Not Certified | Not Verified |
5 | Gorakhpur | Bansgaon | Lalpur | 456153 | Lalpur | 419 | 419 | 100 | Har Gar Jal | Not Certified | Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 54 | 54 | Yes | 0 | NA | No | 12944.00 | 17989.00 |