Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20097674
SCHEME NAME
CHAK JAINAB W/S SCHEME (HFCL)
ESTIMATED COST
366.89
EXPENDITURE
137.59
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
19329.00
Meter
Length Laid
10582.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | Chak Jainab | 473199 | Chak Jainab | 268 | 262 | 98% | Work In Progress | Not Certified |
| 2 | Ghazipur | Kasimabad | Chak Jainab | 473200 | Chak Mukri | 76 | 74 | 97% | Work In Progress | Not Certified |
| 3 | Ghazipur | Kasimabad | Chak Jainab | 473201 | Chak Dariya | 50 | 46 | 92% | Work In Progress | Not Certified |
| 4 | Ghazipur | Kasimabad | Chak Jainab | 473202 | Surji Pati | 89 | 84 | 94% | Work In Progress | Not Certified |
| 5 | Ghazipur | Kasimabad | Chak Jainab | 473203 | Chak Badul | 47 | 45 | 96% | Work In Progress | Not Certified |
| 6 | Ghazipur | Kasimabad | Chak Jainab | 473204 | Chamrupur | 7 | 5 | 71% | Work In Progress | Not Certified |