Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20097678 | BHADEV W/S SCHEME (HFCL) | 257.05 | 109.36 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 6983.00 | 8069.40 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Ghazipur | Bhadev | 472823 | Chak Panah Mohammad | 22 | 19 | 86 | Work In Progress | Not Certified |
| 2 | Ghazipur | Ghazipur | Bhadev | 472824 | Bhadev | 319 | 294 | 92 | Work In Progress | Not Certified |
| 3 | Ghazipur | Ghazipur | Bhadev | 472825 | Salarpur | 26 | 23 | 88 | Work In Progress | Not Certified |