Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20097684
SCHEME NAME
CHAUBARA WATER SUPPLY SCHEME
ESTIMATED COST
387.50
EXPENDITURE
99.12
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
26664.00
Meter
Length Laid
26664.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Holagarh | Chaubara | 431821 | Chaubara | 726 | 694 | 96% | Work In Progress | Not Certified |
| 2 | Prayagraj | Holagarh | Chaubara | 431822 | Bardani | 166 | 156 | 94% | Work In Progress | Not Certified |